Tales Event

Guide · 9 min read

At What Wind Speed Should an Outdoor Event Stop? Wind Limits for Stages, Marquees and LED Screens

Short answer: there is no single wind limit that applies to everyone. The limit is the maximum gust speed stated in your structure's design documents, and that figure belongs in the quotation. The most widely used operational value in the industry is 25 m/s, or 90 km/h. The IStructE guide Temporary Demountable Structures (third edition, 2007) sets two alert levels for structures managed to that limit: when the gust speed measured 10 metres above ground exceeds 19.4 m/s (roughly 70 km/h) the crew goes on alert, and when it exceeds 22.3 m/s (roughly 80 km/h) the management plan is implemented and the site is closed to the public. Those thresholds are not arbitrary. The first corresponds to 60 percent of the operational load, the second to 80 percent. Build-up has its own limit. ESTA's ANSI E1.21-2023 standard treats 40 mph, about 64 km/h, as an established threshold above which working at height is considered unsafe. A small single-guyed marquee sits lower still, at around 18 m/s or 65 km/h. Below: where these thresholds come from, why marquees, stages, backdrops and LED screens each have a different limit, where the anemometer goes, and what to demand in writing.

What happens at what speed? Two alert levels

Section 8 of the IStructE guide states the rule plainly: design documents should clearly state the maximum gust wind speed at which the structure remains stable. For a new design there are two routes. Either you design for the highest wind force likely to be experienced, which rarely makes economic sense outside heavy crane-erected frameworks, or you set an operational limit and measure the wind on site. When the second route is chosen, the value the guide suggests is 25 m/s, or 56 mph. Table 8 of the guide turns that limit into three numbers. With the anemometer at 10 metres, the operational limit is 25 m/s (90 km/h), Level 1 is 19.4 m/s (about 70 km/h) and Level 2 is 22.3 m/s (about 80 km/h). At Level 1, with recorded speeds trending upward, staff are put on alert and further erection is reconsidered if build-up is still under way. At Level 2 the procedures in the management plan are implemented and the site is secured against public access. Raise the measuring point and the numbers rise with it, because the reference height is 10 metres: at 5 metres they become 21.5, 16.7 and 19.2 m/s, and at 30 metres 27.5, 21.4 and 24.6 m/s. If your structure's limit is not 25 m/s, all three numbers change. The useful question is not how hard the wind is blowing, but what the structure was rated to hold.

Why does a 40 percent rise in speed double the load?

Wind pressure scales with the square of wind speed, not with speed itself. The basic relationship in EN 1991-1-4 is dynamic pressure = 0.5 x air density x velocity squared, and clause 4.5 gives 1.25 kg per cubic metre as the recommended air density. Run the numbers and you get roughly 12 kilograms per square metre at 50 km/h, 21 at 65 km/h, 24 at 70 km/h, 31 at 80 km/h, 40 at 90 km/h and 49 at 100 km/h. The warning hidden in that list: going from 45 km/h to 90 km/h does not double the load, it quadruples it. A concrete example puts it in scale. A 6 metre by 3 metre LED wall presents 18 square metres of surface, and a 90 km/h gust pushes it sideways with roughly 700 kilograms of force. That is the raw dynamic pressure; the real force is worked out with shape-dependent coefficients, and for a flat solid panel it does not come down. The reference for permanent buildings is a useful comparison. EN 1991-1-4 defines basic wind speed as a 10-minute mean measured 10 metres above open terrain, and Turkish steel design practice takes 28 m/s as the lower bound for that value. A permanent building is sized for that speed. A stage that stands for three days is not, which is exactly why measurement and a plan are mandatory.

At what size does a marquee fall under the standard?

The threshold is 50 square metres. EN 13782, adopted in Turkey as TS EN 13782, covers the safety of design, calculation, manufacture, installation and maintenance for mobile, temporarily installed tents with more than 50 square metres of ground area. One detail catches people out: the standard also applies to groups of smaller tents that are installed close together and exceed 50 square metres in total. Pitching five small marquees side by side does not put you outside the scope. The standard requires verification of stability against overturning, sliding and lifting, along with test protocols for the load-bearing capacity of weight and rod anchorages. Size definitions matter too. Pole marquees spanning more than 12 metres and framed marquees spanning more than 9 metres count as large marquees, and those need a maximum service gust speed backed by structural calculation. Small marquees have practical limits drawn from long experience: single-guyed, they can be used up to Beaufort Range 5, a gust equivalent of about 18 m/s (65 km/h); double-guyed, up to Beaufort Range 7, about 27 m/s (97 km/h). Double-guying raises a marquee's rated value by a factor of about 1.4, so the guying arrangement belongs in the quotation. There is a trade-off worth pricing. If a marquee is rated at 90 percent of the site's maximum service gust speed it will be unusable for about 25 hours a year; at 80 percent that becomes 100 hours, at 70 percent 500 hours, and at 60 percent 2,500 hours. A cheap marquee is not cheap, it is a purchase of cancellation risk.

Why does a backdrop lower a stage's wind limit?

The same stage becomes a different structure the moment you stretch fabric across it. IStructE treats stages separately, and the reasoning fits in one sentence: because of their relatively large superstructure face area, the wind case is almost always critical, so stages have to be managed structures. The guide also notes that adding banners, cladding and the like significantly increases wind loading and therefore raises the risk of overturning or collapse. How much of a surface counts as closed is not left to guesswork either. Solid riser stands are assessed at 90 to 100 percent blockage, open riser stands at 50 to 75 percent. In practice, advertising banners, wing scrims and LED screens are sails. ANSI E1.21-2023 permits load reduction by removing elements one at a time, but sets a floor: with those elements in place, the reduced design wind speed shall not be less than 40 mph, about 64 km/h. The standard's sample operations management plan works in three steps: at the first speed personnel go on alert, at the second they stand by to remove the element, at the third they remove it. Each element gets its own speed. Backdrop, sound wing scrims, lowering the speaker cabinets and lowering the roof are separate lines. The right moment to strip a stage is hours ahead of the forecast, not after the wind arrives.

Where does the anemometer go, and what does it measure?

Measure from the wrong place and the thresholds mean nothing. IStructE defines the operational maximum gust as a one-second gust measured 10 metres above ground level. The ideal setup is a 10 metre mast standing at least 60 metres clear of large obstructions, trees and buildings. Where that is impractical the anemometer is fixed to the structure itself, mounted at a height of at least 1.3 times the structure's maximum height plus one metre. Monitoring runs continuously for as long as people are on or around the structure. An audible or visual alarm is required for both alert levels, and once a Level 1 action has been triggered a hard copy of the wind record is kept for inspection. ANSI E1.21-2023 describes the same job slightly differently: active on-site monitoring is maintained for the entire period the structure is assembled, the weather station is placed within five feet of the highest production element and clear of anything that might shield it from the wind, and recording becomes continuous once a triggering threshold is reached. A small but expensive detail: most units can trigger only one alarm, and many ship with a fixed cable length of around 20 metres that cannot be extended. If your plan has two levels, confirm this before you order.

Should a weather warning stop the event?

Turkey's meteorological service, MGM, runs a four-colour warning system called MeteoUyari. Green means no event warranting a warning is forecast. Yellow means the weather is potentially dangerous and the conditions call for caution. Orange means the weather is dangerous, an infrequent event likely to cause damage that needs close monitoring. Red means very dangerous conditions with a threat to life across a wide area. The system covers twelve hazards, strong wind and storms among them. A colour code is valuable for planning, but it is not a trigger. ANSI E1.21-2023 draws that line explicitly: national weather service advisories shall be considered a last resort source of information and shall not be used as a triggering threshold for the mitigating actions in the operations management plan. The reasoning is straightforward, since such warnings are typically issued when conditions are already occurring or have occurred. What the standard asks for instead is an honest arithmetic of time. Compare how long the mitigating action takes against the fastest anticipated weather approach rate and the lead time of the forecast, and have a qualified person validate the thresholds against that comparison. The decision on site is made by the anemometer on site. The colour code tells you how many hours you have before that decision arrives.

Why is evacuation the last resort? Indiana, 2011

At 8.46 pm on 13 August 2011, a gust from an approaching thunderstorm struck the roof structure of a temporary outdoor concert stage at the Indiana State Fair. The structure came down into the crowd, killing seven people and injuring 58. The measured gust was around 59 mph, roughly 95 km/h, while the applicable building code required the structure to withstand 68 mph, about 109 km/h. The Thornton Tomasetti engineering report attributed the failure to the inadequate capacity of the lateral load resisting system, which consisted of guy lines connected to concrete Jersey barrier ballast. Those barriers, as arranged that night, could resist winds of only 25 to 43 mph (40 to 69 km/h) depending on direction. The report recorded a second gap as well: the state fair commission lacked formal protocols for delaying, postponing or cancelling a production. ANSI E1.21-2023 describes evacuation as the alternative of last resort and requires a formal risk assessment by qualified persons if it forms part of the plan, because moving a crowd while a storm closes in generates risk of its own. The order the standard prefers is to lighten the structure first, strengthen it second, and evacuate last. And who holds the authority to suspend the event, and how that decision is communicated, is agreed in writing before the event.

What to demand in writing

For outdoor work a quotation is less a price list than a safety document. Ask for these nine lines in writing: the maximum gust speed at which the structure remains stable and which configuration that figure applies to (backdrop fitted or not, LED screen hung or not), the separate wind limit that applies during build-up and strike, the anchoring or ballast method and its calculated holding capacity, the guying arrangement and ground area for marquees, the make of the anemometer, the height it will be mounted at and the alert levels, the removal speed for each element and how many minutes removal takes, who monitors the weather and from which source, who holds the authority to stop the event, and which standard the structural calculations follow. Without those lines you are not holding a quotation, you are holding a guess. Tales Event is based in Istanbul and delivers stage, marquee, LED screen, sound and lighting builds with a single crew across Turkey, for openings, launches, dealer meetings, gala nights and graduation ceremonies. Send us the site location, the stage and screen dimensions you have in mind and the date, and we will come back with wind limits, an anchoring plan and action thresholds backed by written calculation.

Let's talk about your event

Tell us your idea and we will prepare the concept and quote.